We are progressing plans to demolish Alexandra House and Hillsborough House in Weston-super-Mare. 

Both buildings are now empty, and demolition works will begin in summer 2026. This page provides the latest information about what is happening, when, and what to expect. 

Weaver

Meet the contractor

We’re holding a drop-in event where you can meet the team carrying out the demolition works and ask any questions you may have. 

When: Tuesday 23 June - drop in anytime between 3pm – 7pm 

Where: Bournville Community Hub, The Sub Station, St Andrews Parade, BS23 3SS 

You’ll be able to speak directly with Weaver Demolition Ltd and find out more about what to expect during the works. 

Background

In 2025, following detailed surveys and expert advice, we made the decision to demolish Alexandra House and Hillsborough House.

Both buildings are over 60 years old and would require significant investment to bring them up to modern standards. Even with this investment, they would not provide the quality of homes we want for our customers in the long term.

This was not a decision we took lightly. Since then, we have been working closely with customers to support them to move into new homes. All households have now been successfully rehoused, and both buildings have been empty since March 2026.

 

Demolition works

We have appointed Weaver Demolition Ltd to carry out the demolition works.

The works will take place in phases and will be carefully managed to ensure safety and reduce disruption as much as possible.

 

Alexandra House 

Start on site: 22 June 2026

Completion: autumn 2026

What will happen

The works will take place in stages:

Site set-up (approx. 1 week)

  • Installation of site offices and welfare facilities
  • Erection of hoarding and secure fencing

Asbestos removal and stripping out the interior of the building (approx. 4 weeks)

  • Safe removal of any asbestos by licensed specialists
  • Removal of internal fixtures such as ceilings, doors, wiring and fittings

Main demolition (approx. 8–10 weeks)

  • The building will be taken down gradually using specialist machinery
  • Work will be carried out from the top down in controlled sections

Ground works and site clearance (approx. 4 weeks)

  • Removal of foundations and slabs
  • Crushing and recycling of materials where possible
  • Final site clearance and installation of permanent hoarding

 

Hillsborough House 

Start on site: mid-August 2026

Completion: anticipated before Christmas 2026

What will happen

The works will follow a similar approach to Alexandra House:

  • Site set-up and fencing
  • Asbestos removal and preparation
  • Gradual demolition of the building
  • Site clearance and securing the site

 

Working hours

Monday to Friday: 7.30am to 6pm

Saturday: 8am to 1pm

No work will take place on Sundays and bank holidays.

No loud machinery or mechanical equipment will be used before 08:30am. 

We are also imposing restrictions on HGV movement during school drop off and pick up times from 8:15am to 9:15am, and from 2:30pm to 3:45pm.

 

What to expect

During the works, you may notice:

  • Noise and vibration
  • Increased construction traffic
  • Temporary changes to pedestrian routes

 

How we are reducing disruption

Our contractor will work to minimise impact by:

  • Using water sprays to control dust
  • Managing vehicle movements safely
  • Keeping turning within the site where possible
  • Putting measures in place to protect pedestrians and cyclists

 

Local arrangements

To support the demolition works, the car park at the junction of Lonsdale Avenue and Windwhistle Lane has been closed and is being used as the contractor’s site base. This will remain closed until December 2026.

Temporary changes to nearby footpaths will also be in place, with alternative routes clearly signposted.